                                                                       04/19/91
                                    JULLS LONG REPORT

            1. (U) JULLS NUMBER: 31331-23623 (00123), submitted by RILEY
            AFZN-ST, LTC JOHNSON, 856-6846, (913)239-6846.

            2. (U) Operation DESERT SHIELD conducted by USCENTCOM on 02/11/91.

            3. (U) KEYWORDST RWO (REAL WORLD OPS), USA (US ARMY), ACTIVE
            COMPONENT, C2 (COMMAND AND CONTROL), AVAILABILITY, COORDINATION,
            PLANNING.


            4. (U) TITLE: C2: COORD BETWEEN INCREMENTS OF IST ID G-STAFF
            FAILED DURING DEPLOYMENT

            5. (U) OBSERVATION: The movement and handoff of responsibilities
            between division B-Sta+f increments while deploying from Fort
            Riley to the APOD, SPOD, and TAA was unorchestrated. Division
            staff members departed immediately for the TAA upon arriving in
            country.

            6. (U) DISCUSSION: B-Sta++ members were not available to assist
            subordinate units at port with coordination/supply problems; eg,
            S2 rep was needed to obtain maps. LNO at port was required to
            resolve problem areas which they did not have the expertise nor
            time to handle.

            7. (U) LESSON LEARNED: a. A representative from each G-Staff
            activity should be a part of the liaison staff at SPOD to
            provide assistance to arriving divisional units.

                b. A HO Commandant representative also should be part of
            the liaison staff at the SPOD.


            S. (U) RECOMMENDED ACTION: DIVISION: Implement lesson learned.

            9. (U) COMMENTS-    none



            --- (U) SUBJECT: COMMAND & CONTROL

                (U) INTEROPSRABILITY.- PLANNING

                (U) Action managed by: LOCAL, action worked by: , RAP number:
                 Lesson distributed by: LOCAL.














           UNCLASSIFIED

Document Page: First | Prev | Next | All | Image | This Release | Search


Document 517 f:/Week-26/BX001008/DESERT STORM AFTER ACTION REPORTS/special information for installation after actio:12179611150511
Control Fields 17
File Room = jul96_declassified
File Cabinet = Week-26
Box ID = BX001008
Unit = 1ST ID
Parent Organization = VII CORPS
Folder Title = DESERT STORM AFTER ACTION REPORTS
Folder Seq # = 11
Subject = SPECIAL INFORMATION FOR INSTALLATION AFTER ACTIO
Document Seq # = 4
Document Date =
Scan Date =
Queued for Declassification = 01-JAN-1980
Short Term Referral = 01-JAN-1980
Long Term Referral = 01-JAN-1980
Permanent Referral = 01-JAN-1980
Non-Health Related Document = 01-JAN-1980
Declassified = 17-DEC-1996