Document Page: First | Prev | Next | All | Image | This Release | Search

File: 123096_jul96_decls1_0293.txt
Page: 0293
Total Pages: 517

Subject: SPECIAL INFORMATION FOR INSTALLATION AFTER ACTION REPORT        

Unit: 1ST ID      

Parent Organization: VII  CORPS  

Box  ID: BX001008

Folder Title: DESERT STORM AFTER ACTION REPORTS                                                               

Document Number:          4

Folder Seq  #:         11






                                     UNCLASSIFIED
                                                                     04/19/91
                                   JULLS LONG REPORT

          1. (U) JULLS NUMBER: 22634-64310 (O()009), submitted by RILEY
          HSBY-D, CPT OWENS, e56-4429, (91-1)239-4429.

          2. (U) Operation DESERT SHIELD conducted by USCENTCOM on O./Ol/91.

          3. (U) KEYWORDS: PLANNING, RWO (REAL WORLD OF,S), USA (US ARMY),
          GUARD COMPONENT, RESERVE COMPONENT, MOBILIZATION, LOGISTICS,
          TRANSPORTATION, AVAILABILITY, COORDINATION, SHORTAGE, CRIT4 (OTHER
          OBSERVATION), INPROCESSING.

          4. (U) TITLE-. LOGISTICS: TRANSPORTATION: DENTAC DID NOT HAVE
          PRIORITY USE OF BUSES


          5. (U) OBSERVATION: All mobilized soldiers were transported to
          the dental clinics for processing. DENTAC did not have priority
          to obtain buses.

          6. (U) DISCUSSION: In order to properly evaluate mobilized
          soldiers, DENTAC must have two buses to transport soldiers to
          dental clinics. I+ DENTAC does not have priority, the POR
          process is slowed down, which directly impacts on further
          deployment.

          7. (U) LESSON LEARNED: Two buses must be reserved +or DENTAC
          during RC unit mobilization.

          B. (U) RECOMMENDED ACTION:

             a. OOL-. Identify two buses +or DENTAC use during RC unit
          mobilization.


             b. (alternate) DENTAC-. Coordinate with Contracting to
          prepare an on-the-shelf contract +or two buses with drivers to
          be activated during RC unit main body inprocessin g.

          9. (?) COMMENTS:



          --- (U) SUBJECTI LOGISTICS


              (U) INTEROPERABILITY: PLANNING

               (U) Action managed by.- LOCAL, action worked by: RAF' number:
               Lesson distributed by: LOCAL.












                                     UNCLASSIFIED


                                        @-/. 3

Document Page: First | Prev | Next | All | Image | This Release | Search


Document 517 f:/Week-26/BX001008/DESERT STORM AFTER ACTION REPORTS/special information for installation after actio:12179611150511
Control Fields 17
File Room = jul96_declassified
File Cabinet = Week-26
Box ID = BX001008
Unit = 1ST ID
Parent Organization = VII CORPS
Folder Title = DESERT STORM AFTER ACTION REPORTS
Folder Seq # = 11
Subject = SPECIAL INFORMATION FOR INSTALLATION AFTER ACTIO
Document Seq # = 4
Document Date =
Scan Date =
Queued for Declassification = 01-JAN-1980
Short Term Referral = 01-JAN-1980
Long Term Referral = 01-JAN-1980
Permanent Referral = 01-JAN-1980
Non-Health Related Document = 01-JAN-1980
Declassified = 17-DEC-1996