                                                                      04/19/91
                                    JULLS LONG REPORT

           1. (U) JULLS NUMBER: 30455-66978 (00057), submitted by RILEY
           AFZN-EN-YO, CPT WOODS, 856-4210, (913)239-4210.

           2. (U) Operation DESERT SHIELD conducted by USCENTCOM on 02/06/91.

           3. (U) KEYWORDS: RWO (REAL WORLD OPS), USA (US ARMY), ACTIVE
           COMPONENT, LOGISTICS, TRANSPORTATION, AIRLIFT, FAVORABLE,
           COORDINATION, INTEROPERABILITY, PLANNING.

           4. (U) TITLE: LOGISTICS: PRE-ATRFLOW MEETING & DACS INFORMATION
           PACKET

           5. (U) OBSERVATION: Conducting pre-air+low meetings with unit
           commanders and movement officers paid tremendous dividends when
           it came time to deploy.

           6. (U) DISCUSSION: We found it most successful to distribute
           information packets with as much information about the DACS
           process as possible, and then conduct the pre-airflow meetings
           as a question and answer session'. We also found that inviting
           brigade XOs, movement officers, and staff led to the most
           efficient dissemination of information.

           7. (U) LESSON LEARNED: Pre-air+low meeting with unit/sta+4
           personnel alleviated problems/qLtestions prior to actual unit
           movement.

           S. (U) RECOMMENDED ACTION: As early as possible, assemble a
           DACG information packet and distribute it to all unit commanders
           on the installation. Periodically update the packet and
           distribute changes.

           9. (U) COMMENTS:    none



           --- (U) SUBJECT: LOGISTICS


                (U) INTEROPERABILITY: PLANNING

                (U) Action managed by: LOCAL, action worked by:  RAP number:
                Lesson distributed by: LOCAL.















                                      UNCLASSIFIED


       l@ - 'Yo

Document Page: First | Prev | Next | All | Image | This Release | Search


Document 517 f:/Week-26/BX001008/DESERT STORM AFTER ACTION REPORTS/special information for installation after actio:12179611150511
Control Fields 17
File Room = jul96_declassified
File Cabinet = Week-26
Box ID = BX001008
Unit = 1ST ID
Parent Organization = VII CORPS
Folder Title = DESERT STORM AFTER ACTION REPORTS
Folder Seq # = 11
Subject = SPECIAL INFORMATION FOR INSTALLATION AFTER ACTIO
Document Seq # = 4
Document Date =
Scan Date =
Queued for Declassification = 01-JAN-1980
Short Term Referral = 01-JAN-1980
Long Term Referral = 01-JAN-1980
Permanent Referral = 01-JAN-1980
Non-Health Related Document = 01-JAN-1980
Declassified = 17-DEC-1996