Document Page: First | Prev | Next | All | Image | This Release | Search
File: 123096_jul96_decls1_0354.txt
Subject: SPECIAL INFORMATION FOR INSTALLATION AFTER ACTION REPORT
Unit: 1ST ID
Parent Organization: VII CORPS
Box ID: BX001008
Folder Title: DESERT STORM AFTER ACTION REPORTS
Document Number: 4
Folder Seq #: 11
UNCLASSIFIED
04/19/91
JULLS LONG REPORT
1. (U) JULLS NUMBER: @274e-i9393 (Oo251), submitted by RILEY
AFKB-RG-FR, CPT KING, e56-3336, (913)239-3336.
2. (U) Operation DESERT SHIELD conducted by USCENTCOM on 03/13/91.
3. (U) KEYWORDS: TRANSPORTATION, TRANSPORTATION ASSETS, PLANNING,
RWO (REAL WORLD OPS), USA (US ARMY), (3UARD COMF-ONENT, RESERVE
COMPONENT, C2 (COMMAND AND CONTROL), MOBILIZATION, EQUIPMENT,
UNFAVORABLE, COORDINATION, PRIORITY, SUPF,ORTABILITY, MATERIEL,
CRIT2 (SERIOUS PROBLEM).
4. (U) TITLE: LOGISTICS: SHORTAGE OF TRANSPORTATION RESOURCES
5. (U) OBSERVATION: Shortages of CONEX containers and MILVANS
were experienced at mobilization station.
6. (U) DISCUSSION: The shortage of CONEX containers and MILVANS
after the deployment of the Ist Infantry Division (M) affected
the deployment dates of the 410th Evacuation Hospital. Due to
this shortage, a commercial transportation company was contacted
to supply shipping containers and move the equipment. This
resulted in a lengthening of shipping time for the Ltnit's
vehicles and CTA deployable equipment. This raised the
potential of unit personnel being in Country 2-3 weeks before
the arrival of tentage and equipment necessary to house and feed
the unit. Because of this situation, ship dates and contractors
were renegotiated and deployment dates were again lengthened. It
was 69 days after being mobilized be-Fore the 410th Evacuation
Hospital deployed to the theater of operation. Similar
Situations took place with the 170th Maintenance Co., and the
403rd F'W Camp.
's Must plan
for RC unit transportation requirements.
S. (U) RECOMMENDED ACTION: AUEL data for all deploying units
Must be compared with existing transportation resources at the
mobilization station. Units will continue to deploy and require
resources after the Ist ID (M) departs.
9. (UY-COMMENTS: none
--- (U) SUBJECT: LOGISTICS
(U) INTEROPERABILITY: PLANNING
(U) Action managed by: LOCAL, action worked by: RAP number.
Lesson distributed by, LOCAL.
UNCLASSIFIED
Document Page: First | Prev | Next | All | Image | This Release | Search
Document 517 f:/Week-26/BX001008/DESERT STORM AFTER ACTION REPORTS/special information for installation after actio:12179611150511
Control Fields 17
File Room = jul96_declassified
File Cabinet = Week-26
Box ID = BX001008
Unit = 1ST ID
Parent Organization = VII CORPS
Folder Title = DESERT STORM AFTER ACTION REPORTS
Folder Seq # = 11
Subject = SPECIAL INFORMATION FOR INSTALLATION AFTER ACTIO
Document Seq # = 4
Document Date =
Scan Date =
Queued for Declassification = 01-JAN-1980
Short Term Referral = 01-JAN-1980
Long Term Referral = 01-JAN-1980
Permanent Referral = 01-JAN-1980
Non-Health Related Document = 01-JAN-1980
Declassified = 17-DEC-1996